A recurring leak near kitchen equipment
The roof had a history of leakage near equipment serving the restaurant. Earlier caulk, peel-and-stick patches and coatings surrounded the area, and the assessment also found standing water near several drains.
The temporary repair work
The October service work focused on two seams, two corners and boot flashing. The closeout photographs show treated details around equipment and a penetration within the existing roof.
A longer-term restoration option
The separate proposal considered cleaning, preparation, localized repairs and GAF High Solids Silicone Roof Coating over the restaurant roof. Drainage reconstruction, neighboring tenant roofing and structural work would require their own scopes.
Before and after the service
The gallery includes the October 12 condition photographs and the October 21–22 repair photographs. Together they show the layered repair history and the locations that received temporary attention.
Project details
- Property
- Restaurant in Idaho Falls, Idaho
- Assessment
- October 12, 2026; 20-image condition record
- Reported repair scope
- Two seams, two corners and boot flashing
- Work stage
- October 21 repairs; October 22 closeout photographs
- Area limit
- Restaurant roof area; neighboring tenant work not included
Project timeline
October 12, 2026
Condition assessment and 20-image record of ponding, prior patches and equipment-area conditions.
October 13, 2026
Separate restoration and temporary-repair options documented.
October 15, 2026
Temporary repair approval recorded.
October 21, 2026
Contractor reported repairs to two seams, two corners and boot flashing.
October 22, 2026
Completed-repairs photo package supplied and forwarded; image groups include October 21 and 22 dates.